  • At 08h30 my group was ordered to disconnect the overhead line suffix cable to make it underground cable,we started by digging a 12m trench,disconnect and isolate the cable make a joint after that we buried the cable, connect the supply and test for voltage,we finished the job at 11h30,the job was instructed to us by Mr Etian.